In any project the intended outcomes need to be identified. It is vital in a collaborative project for the intention of the project to be explicitly known to all members, this way each individual can contribute to the evaluation and implementation of the intended outcomes. The evaluation could become continuous processes to make sure project is heading toward the right outcomes.[1] See figure 1.

Figure1. Outcome cycle - for continuous evaluation of intended outcomes
Just like goals, intended outcomes needs to be realistic and achievable and can be set in short term intentions and long term intentions. This way budget and timeline can be accurately allocated. In a project the outcome intention is not always achievable, e.g. untended budget spend. A project found itself in this situation after reviewing its outcome, they found two unintended outcomes one was the unintended role of the some of the members and to what extent they should try to complete their task when there are constraints and the second was the unintended time committed to tasks.[2] Unintended outcomes are apparently common due to constraints and unforeseeable events.
It has been noted down that project manager are responsible for managing the “…overall intention of the project, and to the specific description of the desired final product”, which is only reasonable as they are the one who set time frame, estimate costs on tasks and have the responsibility to make decision if more time is needed to complete a certain task.[3]
Intention can be proven through many different forms of communication whether through speech, written form, or any other visual form. The intention of the project must be addressed from the start to finish, this way goal and objective can be achieve effectively and efficiently.
In relating back to the fabrication task, each group should have an intended outcome to better plan out the tasks required to accomplish the project which in this case fabricating a model in UT3 that is as good as or even better than the falling water model. And the sub criteria to completing this task is to have it completed within due date with all project intended criteria met.
____________________________________
[1] Rick Cummings, “Formative and Summative Evaluation of the Overall Project”, Murdoch University (2004), http://www.tlc.murdoch.edu.au/archive/cutsd99/finalpdfreports/Ch2Evaluation.pdf, viewed on 28 April 2008.
[Figure1] Sara Burns, Sally Cupitt, “The Outcomes Approach”, Homeless outcomes, London Housing Foundation, http://www.homelessoutcomes.org.uk/Outcomes_approach.aspx, viewed on 29 April 2008.
[2] Rick Cummings, op cit.
[3] Martyn Sanjay, “the Specifier guide to Project Management”, Specifier (2007), http://www.specifier.com.au/professionalDirectory/Project-Manager.html, viewed on 27 April 2008.


